Ventura builds a nearly mile-long sand berm as a storm and king tides arrive
The Daily Oxnard team
If you head to the Ventura coast this week, you'll see crews at work. The city began building a nearly mile-long sand berm on Monday to protect coastal properties from large waves, and crews are also working to repair the Ventura Pier.
6 feetexpected height of the berm once it's completed
The berm runs along a vulnerable stretch of Ventura's coastline.
Source: ABC7 Los Angeles
“On those high-tide days, we would be at a pretty high coastal flooding risk without any surf at all.”
- Protects: apartment buildings, homes, businesses and roads
- Ventura Pier: still closed because of large, crashing swells
- High Surf Advisory: ongoing
The waves caused no major problems Monday, but officials are preparing for more storms forecast around Thanksgiving and a Super El Niño expected this rainy season.
The berm was expected to be done in about two days, with more storms ahead
- Nov. 16Crews begin building the nearly mile-long sand berm.
- Nov. 17The berm is expected to be completed.
- Late Nov.Additional storms are forecast around Thanksgiving.
Source: ABC7 Los Angeles
Sources: ABC7 Los Angeles, Ventura County Star